STEP 2
Filing Your Application

After you have met with a planner in the pre-application meeting and you have all required plans and documents together, it is time to submit your project application:

A. The completed application, all required information maps and fees are submitted to
  the Daly City Planning Division, 333 90th Street, Daly City, CA 94015. Applications
cannot be submitted by mail. They must be submitted in person to the Planning Division during regular office hours (Monday through Friday, 8 a.m. to 5 p.m.).

B. Your project/application is assigned a file number, a file is made and the project is
  assigned to a staff planner for evaluation

C. Within 30 days of receiving your application, the Planning Division will determine
  if your application is complete. You will receive written notification explaining whether the application is complete or if we need additional information.

D. If the application is not complete; the project planner will prepare a written list of
  revisions and/or additional information necessary to complete the application. Submission
of the complete application is your responsibility as the applicant. Failure to submit all the information necessary to complete your application will prevent the application from being processed and will result in the delay of your project.

 