GUIDE
TO COMMERCIAL TENANT IMPROVEMENT
A
commercial tenant improvement project involves the interior
remodeling of an existing office or retail space to
upgrade for the present tenant or change to accommodate
a new tenant. This handout is to aid owners, designers
and architects in the preparation of the plans needed
to make application for the necessary permits.
SUBMITTAL
REQUIREMENTS
·
The City of Daly City requires three sets of
plans for tenant improvement projects.
· Five sets are required for large projects when
review by several departments and divisions is required.
· A set of plans consists of a plot plan, drawn
on a 1/8" to 1' scale, and floor plans, drawn on
a 1/4" to 1' scale.
· The plans are to be accompanied with two
copies of Title 24 Nonresidential Energy Calculations.
PLAN
REQUIREMENTS
Plans
must be submitted on 11" X 17" or larger paper.
When
preparing the plans, be certain you include the following
items:
·
Complete floor plans of all levels involved
· Occupant load
· Structural framing details
· Structural calculations
· Anchorage and bracing of walls and equipment
· Location and size of all permanent counters,
tables and displays
· Reflected ceiling plans
· Seismic bracing detail of suspended ceiling
system
· Plumbing, electrical and mechanical plans
· Provide an Electrical Certificate of Compliance
(LTG-1) form and a Mechanical Certificate of Compliance
(MECH-1) form on the plans
Details and notes on the plans should address such items
as:
· Disabled access requirements
· Emergency and exit lighting
· Seismic code requirements
· Exiting
· Occupancy separations and fire walls
· Light and ventilation
· Restroom details
· Any other information necessary to demonstrate
compliance with current codes, local ordinances and
State regulations
Medical
and dental offices and restaurants require additional
information.
· When nonflammable gas cylinders are stored
in medical and dental offices, the plans must include
details of the storage room with one-hour fire rated
walls and proper venting.
· Medical and dental gas systems require special
inspections. Obtain an informational handout at the
Building Division counter.
· Restaurant plans must show details of the cooking
hood, grease ducting and roof outlet. Calculations to
justify the sizing of the cooking exhaust system will
need to be provided. Restaurant applications require
a set of plans reviewed and approved by the San Mateo
County Health Department.
ADDITIONAL
REQUIREMENTS
·
A letter stating the greatest number of employees, which
will be present in the establishment at any one time,
is also required.
· The Daly City Fire Department will require
a set of fire sprinkler plans. They are normally submitted
to the Fire Department after Building permits are issued.
THE
PLAN REVIEW PROCESS
The
City maintains a goal of ten (10) working days turn
around time on review of plans.
Most
Tenant Improvement projects can be processed using Express
Plan Check. Express Plan Check is available on Tuesday
mornings. Plans submitted between 8:00 and 10:00 A.M.
will be reviewed the same day.
·
Following the review of plans, you will receive either
a list of plan check comments, which requires revision
and resubmittal of the plans, or approval of your project.
· If approved, permits may be obtained.
· Permit fees will be provided.
· An application expires if permits are not obtained
within 180 days of initial application.
ADDITIONAL INFORMATION
For
additional building plan review or permit information
call the Daly City Building Division at (650) 991-8061.
For
information regarding fire sprinkler information call
the Daly City Fire Department at (650) 991-8138.
ECDmc041902
|