Daly City Flushing Program 2010 The 2010 flushing program began July 12, 2010 in Zone 4 and is expected to be completed by the end of March 2011 or early April 2011 in Zone 8. Anticipated locations are shown below by month:
Zone 4 – July/August 2010 - COMPLETED
Zone 5 – August/September 2010 - COMPLETED
Zone 6 – September/October/November 2010 - COMPLETED
Zone 7 – November 2010/ December 2010 - COMPLETED
Zone 1 – December/January 2010 - COMPLETED
Zone 3 - January/March 2011 - COMPLETED
Zone 2 – March 2011 - COMPLETED
Zone 8 - April 2011 - COMPLETED