Construction Projects

Enhanced Pedestrian and Bicycle Visibility Improvements

2018EnhancedLogo

The project will install flashing pedestrian signals at three uncontrolled intersections heavily utilized by pedestrians and approximately 10 miles of bicycle routes recommended in the City's current Bicycle Master Plan.   

Location Map

Construction began August 7, 2018 and is anticipated to be completed in January 2019.

City Contact: Roland Yip, Public Works, (650) 991-8155

Alta Loma Tot Lot Renovation

The existing Alta Loma tot lot located along Alta Loma Avenue between Del Prado Drive and St. James Court is being complete renovated. The scope of improvements include new playground structures, playground surfacing, improved drainage, and landscaping.  

Construction will begin September 24, 2018 and is anticipated to be completed in Spring 2019.

City Contact: Jimmy Fu, Public Works, (650) 991-8165

John Daly Boulevard Bridge Streetlights Replacement

The existing streetlight poles and fixtures on the John Daly Boulevard Bridge will be removed and replaced. Due to the constant exposure to fog and salty air, the poles and luminaire arms are rusted and deteriorated beyond repair. The new fixtures will be light emitting diode (LED) and in the same style as the current fixtures but be more energy efficient. Both the streetlights and poles will be painted in the same blue as the original streetlights.

Construction is expected to start in Fall 2019 and be completed by Winter 2019.

City Contact: Jimmy Fu, Public Works, (650) 991-8165

Hickey Boulevard/Campus Drive Crosswalk Improvement

A new crosswalk will be installed at the intersection of Hickey Boulevard and Campus Drive. The project will also include installing new ADA compliant curb ramps on the north and south sides of Hickey Boulevard as well as new sidewalk at the relocated SamTrans bus stop on the south side of Hickey Boulevard. The improvements will provide for better access between the new school and the SamTrans bus stop on the south side of Hickey Boulevard.

Construction is expected to start in January 2019 and be completed by May 2019. 

2018-19 St. Francis Heights Slurry Seal

Since 1998, Daly City Public Works has undertaken a comprehensive street pavement preventative maintenance program that includes an annual Street Slurry Seal Project. Street slurry sealing replaces fine aggregate stripped from the pavement surface, reduces water penetration in the roadway base and thereby reduces base failures and the resultant damage that is much more costly to repair. This year’s project includes the St. Francis Heights neighborhood, and sections of Oriente Street, Ottilia Street, and Schwerin Street.

Construction is anticipated to start in June 2018 and be completed by August 2018.

This project is funded by Senate Bill 1 (SB 1), the Road Repair and Accountability Act.

If you have any questions or concerns, please contact Alexander Yuen, Project Manager, at (650) 991-8064.

THANK YOU FOR YOUR PATIENCE WHILE WE MAKE IMPROVEMENTS TO OUR COMMUNITY!

Notice of Work: English, Spanish, or Tagalog

Notice to Excluded Streets: English, Spanish, or Tagalog

Slurry Seal Schedule with Map. Please check this webpage regularly for updates.